No tasks assigned in PWA

A

andy

I use MSP 2000 and PWA. When I assign resources to a task
they recieve the email notification, but when they go to
the view my tasks page on PWA there are no tasks assigned
to them. When I check the resources page it lists all of
my resources and which tasks are assigned to each one. Am
I missing a step somewhere or do I need to do something in
the admin area to get the task page to show each resource
what there current tasks are?

Any advise would be greatly appreciated.

Thanks,
Andy
 
D

Dale Howard [MVP]

Andy --

Are these tasks more than 10 days in the future? If so, the resource must
click the All Tasks link in the sidepane on the left side of the View My
Tasks page. By default, the system selects the Current Tasks option, which
displays only those tasks that should have started before today, have
started but are not yet completed, and tasks scheduled to begin in the next
10 days. Hope this helps.
 