J
Jakub
Hello,
I have noticed strange thing.
One of the users was added to existing schedule.
After that I see that there is entered work on cube for period of time,
before he was added to schedule.
I have checked user's time sheet and I see that there is scheduled
work for resource for this period of time (work) but nothing was
reported (Act. work is not entered).
Why this is visible on olap cube ? Anybody knows ?
On opened schedule when I try to delete this, I got warning that
it may become out of sync with protected actuals.
Regards,
Jakub
I have noticed strange thing.
One of the users was added to existing schedule.
After that I see that there is entered work on cube for period of time,
before he was added to schedule.
I have checked user's time sheet and I see that there is scheduled
work for resource for this period of time (work) but nothing was
reported (Act. work is not entered).
Why this is visible on olap cube ? Anybody knows ?
On opened schedule when I try to delete this, I got warning that
it may become out of sync with protected actuals.
Regards,
Jakub