C
Comcast News
We are working on an issue for a client, and so far Microsoft has been
unable to find a resoultion to the issue. First, I will give you a little
background information. Our client had a previous installation of Microsoft
Project Server 2002, and they were unhappy with it's performance and bug
issues, so they wanted to upgrade to Microsoft Project Server 2003. We
installed Microsoft Project Server 2003 (all components, using SQL Server
Enterprise, Analysis Server, Windows SharePoint Services) and succesfully
migrated all of there data from SharePoint Team Services and Microsoft
Project Server 2002 into the 2003 version. Some bugs did occur, but we were
able to fix them.
A little while later, they are reporting that anybody that is part of the
enterprise resource pool will now see a task called "NonProject Time." in
web access. The project that is associated with this task (according to
what the TASKS page say's) is called NonProject Time. This project does not
exsist anywhere in Microsoft Project server, we have tried the database
cleanup wizard, and a tool that Microsoft provided us that mass removes
Projects and resources but were unable to find the project anywhere. Upon
checking through EVERY SINGLE OPTION, in Microsoft Project Web server, we
found nothing that could remove these extra taks from displaying. These
tasks were built in 2002, and are no longer needed (or functioning). When
you try to change anything on these tasks, we get an error message "This
task is non working time". I have a screenshot of the TASKS that are
displaying in Microsoft Project Server 2003.
You can view it at: http://www.advisicon.com/NonProject Time.png
These tasks may have manually been added in Microsoft Project Server 2002,
but we don't have this information and the person that originally worked on
2002 is unavailable for comment. I opened a support issue with Microsoft,
but they have not been very helpful with this issue so far. We even
provided them a copy of the SQL database and they were able to reproduce the
issue. There only suggestion so far was to fix the issue in 2002, and the
migrate again. The only issue with this is the fact that the client has
been using Microsoft Project Server 2003 for 3 months, and it has a lot of
new data that we can't afford to lose.
I'm very dedicated to fixing this issue, and have a working duplicate copy
of there system up and running for testing. So if you have any ideas (even
terrible ones), I would be more than happy and able to test them.
unable to find a resoultion to the issue. First, I will give you a little
background information. Our client had a previous installation of Microsoft
Project Server 2002, and they were unhappy with it's performance and bug
issues, so they wanted to upgrade to Microsoft Project Server 2003. We
installed Microsoft Project Server 2003 (all components, using SQL Server
Enterprise, Analysis Server, Windows SharePoint Services) and succesfully
migrated all of there data from SharePoint Team Services and Microsoft
Project Server 2002 into the 2003 version. Some bugs did occur, but we were
able to fix them.
A little while later, they are reporting that anybody that is part of the
enterprise resource pool will now see a task called "NonProject Time." in
web access. The project that is associated with this task (according to
what the TASKS page say's) is called NonProject Time. This project does not
exsist anywhere in Microsoft Project server, we have tried the database
cleanup wizard, and a tool that Microsoft provided us that mass removes
Projects and resources but were unable to find the project anywhere. Upon
checking through EVERY SINGLE OPTION, in Microsoft Project Web server, we
found nothing that could remove these extra taks from displaying. These
tasks were built in 2002, and are no longer needed (or functioning). When
you try to change anything on these tasks, we get an error message "This
task is non working time". I have a screenshot of the TASKS that are
displaying in Microsoft Project Server 2003.
You can view it at: http://www.advisicon.com/NonProject Time.png
These tasks may have manually been added in Microsoft Project Server 2002,
but we don't have this information and the person that originally worked on
2002 is unavailable for comment. I opened a support issue with Microsoft,
but they have not been very helpful with this issue so far. We even
provided them a copy of the SQL database and they were able to reproduce the
issue. There only suggestion so far was to fix the issue in 2002, and the
migrate again. The only issue with this is the fact that the client has
been using Microsoft Project Server 2003 for 3 months, and it has a lot of
new data that we can't afford to lose.
I'm very dedicated to fixing this issue, and have a working duplicate copy
of there system up and running for testing. So if you have any ideas (even
terrible ones), I would be more than happy and able to test them.