Non working time display in the timesheet view

R

Ratnadeep

Hi,

Are there any way to display the non-working time under the timesheet view
in the task page for a member? Currently it shows all the days & it becomes
hard to identify the non-working days from the list of days.Are there any way
we can configure MSP so that it reflects the planned as well as the unplanned
non-working time for any resource on his/her task page?

I am using MS project server 2003 & project professional 2003 .

Thanks,Ratnadeep
 
D

Dale Howard [MVP]

Ratnadeep --

Unfortunately in Project Server 2003, there is no way for team members to
see that days are marked as nonworking time on their View My Tasks page.
Hope this helps.
 