R
Ratnadeep
Hi,
Are there any way to display the non-working time under the timesheet view
in the task page for a member? Currently it shows all the days & it becomes
hard to identify the non-working days from the list of days.Are there any way
we can configure MSP so that it reflects the planned as well as the unplanned
non-working time for any resource on his/her task page?
I am using MS project server 2003 & project professional 2003 .
Thanks,Ratnadeep
Are there any way to display the non-working time under the timesheet view
in the task page for a member? Currently it shows all the days & it becomes
hard to identify the non-working days from the list of days.Are there any way
we can configure MSP so that it reflects the planned as well as the unplanned
non-working time for any resource on his/her task page?
I am using MS project server 2003 & project professional 2003 .
Thanks,Ratnadeep