P
poelski
I have done all of the needed steps when entering vacation for a resource. I
opened the enterprise resource pool, clicked on the resource, clicked the
working time tab, selected the time period, clicked non-working time in the
upper right, did not enter a note, then saved and closed. I did all of this
with administrative permissions and seems to have worked. I can go into a
project that the resource is working on and see that dates have now been
pushed out to comply with vacation entered. When a team lead or project
manager views that same project, they can not see the change in time. Any
thoughts or ideas?
opened the enterprise resource pool, clicked on the resource, clicked the
working time tab, selected the time period, clicked non-working time in the
upper right, did not enter a note, then saved and closed. I did all of this
with administrative permissions and seems to have worked. I can go into a
project that the resource is working on and see that dates have now been
pushed out to comply with vacation entered. When a team lead or project
manager views that same project, they can not see the change in time. Any
thoughts or ideas?