non-working time not being seen

P

poelski

I have done all of the needed steps when entering vacation for a resource. I
opened the enterprise resource pool, clicked on the resource, clicked the
working time tab, selected the time period, clicked non-working time in the
upper right, did not enter a note, then saved and closed. I did all of this
with administrative permissions and seems to have worked. I can go into a
project that the resource is working on and see that dates have now been
pushed out to comply with vacation entered. When a team lead or project
manager views that same project, they can not see the change in time. Any
thoughts or ideas?
 
D

Dale Howard [MVP]

poelski --

Ask the project manager or team lead to apply the Resource Sheet view, to
double-click on the resource's name, and to examine the Working Time and
Notes tabs. The information should appear there. Hope this helps.
 
P

poelski

Still have the same problem with non-working time not being seen, by team
leads/project managers. Tried what Dale said to do and still no luck. Is
there a setting that I could be missing on the Project Web Access server that
is not pushing out the change, or should a change to the enterprise resource
pool be automatic?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top