R
Ratnadeep
Hi ,
I am facing a weird problem with our PMO. We are using Pro server 2003 along
with project professional 2003.
We are managing our non-working times through a separate project for every
team where each team members fill up their own unplanned activities. The
problem is with the tracking the vaction time & displaying it in the web page
under resource availability view.
We are managing the non-working times through each resources individual
calendars e.g. blocking the particular days as non-working time. But when we
are trying to analyse the resource availability it is not displaying the
updated data. It is only showing the planned working hours for each day
irrespective of the data entered in the resource calendar. e.g our planned
working hour /day is 6 hours.So it is showing 30 hours/week even if the
resource is out for that entire week. This is representing a wrong data for
the executives. Am i missing any steps or tricks? Can someone please advice?
Thanks,Ratnadeep Banerjee,PMP
I am facing a weird problem with our PMO. We are using Pro server 2003 along
with project professional 2003.
We are managing our non-working times through a separate project for every
team where each team members fill up their own unplanned activities. The
problem is with the tracking the vaction time & displaying it in the web page
under resource availability view.
We are managing the non-working times through each resources individual
calendars e.g. blocking the particular days as non-working time. But when we
are trying to analyse the resource availability it is not displaying the
updated data. It is only showing the planned working hours for each day
irrespective of the data entered in the resource calendar. e.g our planned
working hour /day is 6 hours.So it is showing 30 hours/week even if the
resource is out for that entire week. This is representing a wrong data for
the executives. Am i missing any steps or tricks? Can someone please advice?
Thanks,Ratnadeep Banerjee,PMP