Non working time not diplaying in the "View Resource availability"

R

Ratnadeep

Hi ,

I am facing a weird problem with our PMO. We are using Pro server 2003 along
with project professional 2003.
We are managing our non-working times through a separate project for every
team where each team members fill up their own unplanned activities. The
problem is with the tracking the vaction time & displaying it in the web page
under resource availability view.
We are managing the non-working times through each resources individual
calendars e.g. blocking the particular days as non-working time. But when we
are trying to analyse the resource availability it is not displaying the
updated data. It is only showing the planned working hours for each day
irrespective of the data entered in the resource calendar. e.g our planned
working hour /day is 6 hours.So it is showing 30 hours/week even if the
resource is out for that entire week. This is representing a wrong data for
the executives. Am i missing any steps or tricks? Can someone please advice?

Thanks,Ratnadeep Banerjee,PMP
 
A

Andrew Lavinsky

If I follow your e-mail, it sounds like your method would simply introduce
overallocations to the resources. The system won't reschedule work, but
display the resources as overallocated on each project plan during the vacation
period. It's up to each PM then to level the resources.

Try opening one of the projects with work assigned during the vacation period
and review the Resource Usage graph to assess if the resource needs to be
leveled.

If I misunderstood your request, please let me know.

- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 
R

Ratnadeep

I see what you are saying but what i am after is: An executive sees the
resource graph & found that for a resource the planned work is showing as 40
hours for a week but the actual work is 0 hours due to the fact that the
resource was on leave on that week. But it is not always possible for the
management to know that & it is not reflected from the resource utilisation
sheets. So they feel that either the data is not updated properly or there
had been no work done. How to make the non-working times visible to the
people higher up? Hope i am able to explain correctly. Do let me knwo if you
need anymore info.

Thanks,Ratna
 
A

Andrew Lavinsky

If the PMs are adjusting work to the individual calendars and reviewing overallocations,
the planned work for the vacation week should be 0. Sounds like a PM training
issue to me.

If I were the PM, I'd be using the Resource Graph to periodically review
allocations, and make sure that the Planned Work is accurate.


- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 
R

Ratnadeep

Thanks Andrew for the response.I will try out the steps & hope things work out.

Thanks,Ratna
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top