J
Janine
I'm having a problem with my enterprise project not reflecting the
non-working times for the enterprise resources.
When I initially created the schedule in project professional, I entered the
non working time in project professional. When I imported the schedule to
project server the non-working time was not reflected.
I found the following steps and followed them:
The Project Server administrator (or Resource Pool administrator) should
perform the following steps to enter nonworking time in the Enterprise
Resource Pool:
Launch Microsoft Project Professional and log into Project Server with
administrator permissions
Click Tools Ø Enterprise options Ø Open Enterprise Resource Pool
Select the resources with nonworking time and then click the Open/Add button
Double-click a resource's name
Select the Working Time tab
Select the dates of the vacation or sick leave days on the calendar, and
then select the Nonworking time option
Click OK
Repeat steps #4-8 for each resource with nonworking time
Save and close the Enterprise Resource Pool
I followed these steps and it still did not not update the non-working time.
Any ideas what may be causing the schedule to not adjust for the non working
times?
Janine
non-working times for the enterprise resources.
When I initially created the schedule in project professional, I entered the
non working time in project professional. When I imported the schedule to
project server the non-working time was not reflected.
I found the following steps and followed them:
The Project Server administrator (or Resource Pool administrator) should
perform the following steps to enter nonworking time in the Enterprise
Resource Pool:
Launch Microsoft Project Professional and log into Project Server with
administrator permissions
Click Tools Ø Enterprise options Ø Open Enterprise Resource Pool
Select the resources with nonworking time and then click the Open/Add button
Double-click a resource's name
Select the Working Time tab
Select the dates of the vacation or sick leave days on the calendar, and
then select the Nonworking time option
Click OK
Repeat steps #4-8 for each resource with nonworking time
Save and close the Enterprise Resource Pool
I followed these steps and it still did not not update the non-working time.
Any ideas what may be causing the schedule to not adjust for the non working
times?
Janine