I am new to Project 2007, havn't used Project in about 4 years.
I can create a new calendar, based upon the Standard calendar, but can not
modify it to accomadate 10 holidays and change the work hours from 8-4 to
7:30- 4:30 for the project I am going to manage. I then want to assign it to
the MS Project file I create.
Q1: How can I accomplish this, I can not determine how to modify and assign
this new calendar?
Q2: Will I have the same issues with Resource calendars, which in some
cases will vary from project's base calendar?
Thank you all very much
Marsh
I can create a new calendar, based upon the Standard calendar, but can not
modify it to accomadate 10 holidays and change the work hours from 8-4 to
7:30- 4:30 for the project I am going to manage. I then want to assign it to
the MS Project file I create.
Q1: How can I accomplish this, I can not determine how to modify and assign
this new calendar?
Q2: Will I have the same issues with Resource calendars, which in some
cases will vary from project's base calendar?
Thank you all very much
Marsh