J
jmh
Is there a way to make a specific task happen on a nonworking day but only
that task? For example, if I schedule "cutover" to take place on Saturday the
10th of April, project gives me the option to make saturday a working day.
Great. But then any tasks that may follow April 9, let's say, will now be
scheduled for April 10. I only want a specific task to be working on
Saturday. Is this possible to do in project? Thanks!
that task? For example, if I schedule "cutover" to take place on Saturday the
10th of April, project gives me the option to make saturday a working day.
Great. But then any tasks that may follow April 9, let's say, will now be
scheduled for April 10. I only want a specific task to be working on
Saturday. Is this possible to do in project? Thanks!