N
novice
While trying to revise already entered hours in PWA we are getting following
error message.
"There is a problem updating some of the the task information because of the
conflicts with the project server database. Contact the server admin about
these tasks. Some actuals on tasks were not updated"
We checked the project plan and the hours entered in PWA and in the project
plan for the task & duration in question and they are nowhere in sync
(Actuals in Project plan are double the actuals in PWA 2003).
Can some one suggest what needs to be done to resolve this issue.
We are using Project Web access 2003, MS Project Professional 2003 and MS
SQL Server 2000.
We are the admins.
error message.
"There is a problem updating some of the the task information because of the
conflicts with the project server database. Contact the server admin about
these tasks. Some actuals on tasks were not updated"
We checked the project plan and the hours entered in PWA and in the project
plan for the task & duration in question and they are nowhere in sync
(Actuals in Project plan are double the actuals in PWA 2003).
Can some one suggest what needs to be done to resolve this issue.
We are using Project Web access 2003, MS Project Professional 2003 and MS
SQL Server 2000.
We are the admins.