E
EL
Hi there,
I've been using MS Project (2000) for quite a while now, but never had to
deal with such a situation.
What do you do when you have a task that cannot be split over a nonworking
time? For instance, if you have a task that requires 2 hours of work and
could start as early as 11am, yet this task cannot be started, paused (for a
lunch break) and completed after, because of the nature of the task.
As such, how can I specify that such a task is not "splittable" and as such
should only be planned to start at 1pm, after lunch in this instance.
I have quite a few hundred such small tasks that cannot be split over any
breaks or pauses and hope there is a way to do this automatically (with
dependencies and constraints) instead of by hand...
Thanks
I've been using MS Project (2000) for quite a while now, but never had to
deal with such a situation.
What do you do when you have a task that cannot be split over a nonworking
time? For instance, if you have a task that requires 2 hours of work and
could start as early as 11am, yet this task cannot be started, paused (for a
lunch break) and completed after, because of the nature of the task.
As such, how can I specify that such a task is not "splittable" and as such
should only be planned to start at 1pm, after lunch in this instance.
I have quite a few hundred such small tasks that cannot be split over any
breaks or pauses and hope there is a way to do this automatically (with
dependencies and constraints) instead of by hand...
Thanks