not showing tasks has remaining hours as 0

R

Raj

I am not able to see any task that has remaining hours 0. What could be the
cause?

Thanks
Raj
 
G

Guidho

If in PWA, click on All tasks instead of current tasks.
If in Project Pro, you probably have a filter applied.

Guidho
 