Notification of Task Completion

C

CQ

Is there a way to notify an assigned resource that the task BEFORE theirs has
completed? This is before any update cycle is run or before any dates move.
In other words, if task one finished a week early, I want the resource
assigned to task two to know that they can start now, even if the update
cycle hasn't moved their dates yet.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top