M
Minhchau
We've been using Project 2003 for about 5 months. I assigned a material
resource to a task at the rate of $1/hr. When the assigned work exceeded
$16,700,000, it showed only $16,666,667 under the cost column for the
assigned task, even the resource estimated cost still showed the correct
amount that I entered (ex: $28,000,000). This was the only resource for that
task, and there was no fixed cost.
Is there a cap on how much a resource can be assigned for each task? If
yes, is there a way that I can increase that cap?
Thanks,
resource to a task at the rate of $1/hr. When the assigned work exceeded
$16,700,000, it showed only $16,666,667 under the cost column for the
assigned task, even the resource estimated cost still showed the correct
amount that I entered (ex: $28,000,000). This was the only resource for that
task, and there was no fixed cost.
Is there a cap on how much a resource can be assigned for each task? If
yes, is there a way that I can increase that cap?
Thanks,