karishma
hi
in the task view and resource view, is it possible to show the nno. of
resources assigned to the task?
i have around 19-20 summary tasks and all of them have about 8-9 subtasks.
now the no. of resources assigned to them is not 1 for all. there might be
2-3 or more resources for single subtask.
so does it possible that project calculate the total no. resources assigned
to the same subtask and enter that no. in assignment unit column (not %)?
hope it makes sense. any help would be great.
in the task view and resource view, is it possible to show the nno. of
resources assigned to the task?
i have around 19-20 summary tasks and all of them have about 8-9 subtasks.
now the no. of resources assigned to them is not 1 for all. there might be
2-3 or more resources for single subtask.
so does it possible that project calculate the total no. resources assigned
to the same subtask and enter that no. in assignment unit column (not %)?
hope it makes sense. any help would be great.