K
KatJ
I'd like to work some customised data into my project file and am not sure
where to start. I've been asked to automate some reporting against Start,
Finish and a custom date field Estimated Finish Date (Date1 with the name
updated). I need to set status against the following scenarios:
1) Green if the duration between a task's Start and Estimated Finish Date is
less than or equal to the duration between the task's Start and Finish Date
2) Amber if the duration between a task's Start and Estimated Finish Date is
between 0% and 10% greater than the duration between the task's Start and
Finish Date
3) Red if the duration between a task's Start and Estimated Finish Date is
greater than 10% longer than the duration between the task's Start and Finish
Date
So, if the task with the following data should be Red
Start - 7 Sept 09
End - 11 Sept 09
Estimated Finish Date - 12 Sept 09
I have some ability in Excel and can do this very readily if I extract the
project data. However, I need to do this in 15 different plans so to avoid
lots of manual work I was hoping I could do it within Project itself.
Based on Excel knowledge, I thought that I might be able to use a customised
field to capture the workdays between Start and Estimated Finish, then use a
traffic light to compare the new duration to the original duration, based on
the status criteria above. This grand plan has failed at the first step as I
can't figure out how to calculate the duration.
Can anyone help me out with this? I have Project 2003 (no access to Project
Server)
Thanks in advance for any assistance!
where to start. I've been asked to automate some reporting against Start,
Finish and a custom date field Estimated Finish Date (Date1 with the name
updated). I need to set status against the following scenarios:
1) Green if the duration between a task's Start and Estimated Finish Date is
less than or equal to the duration between the task's Start and Finish Date
2) Amber if the duration between a task's Start and Estimated Finish Date is
between 0% and 10% greater than the duration between the task's Start and
Finish Date
3) Red if the duration between a task's Start and Estimated Finish Date is
greater than 10% longer than the duration between the task's Start and Finish
Date
So, if the task with the following data should be Red
Start - 7 Sept 09
End - 11 Sept 09
Estimated Finish Date - 12 Sept 09
I have some ability in Excel and can do this very readily if I extract the
project data. However, I need to do this in 15 different plans so to avoid
lots of manual work I was hoping I could do it within Project itself.
Based on Excel knowledge, I thought that I might be able to use a customised
field to capture the workdays between Start and Estimated Finish, then use a
traffic light to compare the new duration to the original duration, based on
the status criteria above. This grand plan has failed at the first step as I
can't figure out how to calculate the duration.
Can anyone help me out with this? I have Project 2003 (no access to Project
Server)
Thanks in advance for any assistance!