M
mansfieldtw
So I've seen similar posts; however, no solutions to this problem.
Using the networkdays formula, I calculated the number of working days
between the due date and the completed date...
=NETWORKDAYS(K1,G1, 'Holiday Chart'!$A$2:$A$18)
where K1=Date Complete (5/1/07)
G1=Due Date (5/1/07)
I would think the result of the formula would = 0, since the due date
and date complete are the same. Instead, the result is 1. Any
suggestions how I can count the number of days in between the 2 dates
to reflect Days Early/Late? Thanks in advance for your help.
-T
Using the networkdays formula, I calculated the number of working days
between the due date and the completed date...
=NETWORKDAYS(K1,G1, 'Holiday Chart'!$A$2:$A$18)
where K1=Date Complete (5/1/07)
G1=Due Date (5/1/07)
I would think the result of the formula would = 0, since the due date
and date complete are the same. Instead, the result is 1. Any
suggestions how I can count the number of days in between the 2 dates
to reflect Days Early/Late? Thanks in advance for your help.
-T