The other thing you can do is to create "Status Lights" in your Enterprise
Global.
You will have to create a formula with graphical indicators, for example:
If RED, then task is overdue,
If YELLOW, then remaining WORK is greater than [Finish-Today()]
If GREEN then task is on time or is comnplete.
Make sure you roll up the formula to Summary Tasks.
And add the Enterprise Task Code to the PWA Project view...
However, with this method, even one little insignificant task being late
could flag the rolled up project sSummary in the PWQA Project view to show it
being not on time.
--
Rick Roszko
PM, MSPS, Network Consultant
dmarti8 said:
We have over 130 projects in Project Server and we want to run a report for
all projects to show what tasks are behind. Is there a way to do that
without opening all of the projects?