F
fullstacks
I have set up my project on a 10 hour a day work schedule. I have most of my
tasks linked from finish to start. The problem is that if one task has a 1
day duration and finishes on Monday, and is linked to its subsequent task in
a FS relationship, the subsequent task is also starting on Monday, not the
following day. There is no lead or lag time assigned to either task. I look
at the work in calendar view and the two tasks overlap a little on the
Monday, but the Gantt chart shows them happening sequentially, with no
overlap. I figure I have the work calendar set up incorrectly.
Why is the software overlapping the work? I don't want any lag or leadt
time. I need the work to happen sequentially. If task 1 finishes on Moday
and has 1 day duration, with no hours or resources assigned to it, then the
following task should begin on Tuesday, right?
tasks linked from finish to start. The problem is that if one task has a 1
day duration and finishes on Monday, and is linked to its subsequent task in
a FS relationship, the subsequent task is also starting on Monday, not the
following day. There is no lead or lag time assigned to either task. I look
at the work in calendar view and the two tasks overlap a little on the
Monday, but the Gantt chart shows them happening sequentially, with no
overlap. I figure I have the work calendar set up incorrectly.
Why is the software overlapping the work? I don't want any lag or leadt
time. I need the work to happen sequentially. If task 1 finishes on Moday
and has 1 day duration, with no hours or resources assigned to it, then the
following task should begin on Tuesday, right?