ok. Big question

R

Ryan

The Help Menu's usually fail to answer subtle mismatches between Web Access
and the Thick Client.

So! Why cant I SEE the individual tasks that should be appearing underneath
projects in the thick clients RESOURCE USAGE VIEW? I can see the plans for
each project, but they dont expand down to reveal the tasks! As far as I
understand this view is un-editable, so I can't just manually add them.

In Web Access, In the View A Project section, I can see the tasks! Why don't
they show up in the thick client? How can I get them to show up? Do they
even paralell?

Any help makes you awesome ;-D
 
A

Amy Lawrance

Hi Ryan,

You can only view tasks of projects which you have open and checked out.
You can modify tasks from multiple projects from this view as long as you
have all the projects you want to modify open. Otherwise it will just show
you a summary task for the project to aid you in your resource allocation
process.

Further, you will need to be the project manager/owner for the projects you
wish to modify in order to be able to open them.

Hope this helps.

Amy
 