Tommy Lovelace
I am an expert user and I'm heavily involved in the local
and global MPUG groups. I get asked this question VERY
often by P3 and SureTrak users that have come over from
the dark side to MSP2K. (I offer free help to these
newcomers by phone and email as a public service to
promote the use of Microsoft Project, especially to those
struggling with the transition.)
Primavera and SureTrak both have a feature that allows one
to 'jump' from a task forwards or backwards to each of its
predecessors or successors in the order of their
succession. Is there a standard feature or an available
subroutine that when run will allow the user to 'jump' to
a task's predecessors/successors, in the order of their ID
#'s (MSP2K)?
Thanks........Tommy Lovelace
and global MPUG groups. I get asked this question VERY
often by P3 and SureTrak users that have come over from
the dark side to MSP2K. (I offer free help to these
newcomers by phone and email as a public service to
promote the use of Microsoft Project, especially to those
struggling with the transition.)
Primavera and SureTrak both have a feature that allows one
to 'jump' from a task forwards or backwards to each of its
predecessors or successors in the order of their
succession. Is there a standard feature or an available
subroutine that when run will allow the user to 'jump' to
a task's predecessors/successors, in the order of their ID
#'s (MSP2K)?
Thanks........Tommy Lovelace