OLAP Capacity Issue

J

Jim Sipe

Running PS 2007 with all latest patches. The Portfolio Analyzer cube is only
showing the months of January and February 2010 for "Capacity" for any
selected resource. "Work" is showing going forward (January thru July). Why
is "Capacity" being time limited to only past months? I have the Capacity
settings for collection set for 36 months for both forward and behind.

Thanks in advance.
 
G

Gary L. Chefetz

Jim:

Let's not split the conversation between threads, it makes it very difficult
to follow. Please revert to the original thread.
 
J

Jim Sipe

I agree, sorry for the duplication, I was not seeing my original post and
thought it did not get entered, could not see how I could delete it. I also
am not getting reply notifications for some reason.
 