We are on Project Server 2003 and have noticed that the last 2 weeks worth of
time entered against a particular project are appearing correctly in Project
Prof and PWA Project Center but are not reflected in the OLAP Cube. We are
in managed periods and utilize the AWP values for reporting.
The server error log does indicate error number 0X800a0005 (viewnotify.cpp)
when this plan is published with a description saying the Views processor
failed to process the following document...ViewsDropData. No data is in the
ViewDrop folder on the server.
The Cube is building successfully, it just does not include the additional
hours logged for the past 2 weeks for this project plan. All other projects
have correct AWP numbers in the Cube.
Any ideas would be appreciated.
time entered against a particular project are appearing correctly in Project
Prof and PWA Project Center but are not reflected in the OLAP Cube. We are
in managed periods and utilize the AWP values for reporting.
The server error log does indicate error number 0X800a0005 (viewnotify.cpp)
when this plan is published with a description saying the Views processor
failed to process the following document...ViewsDropData. No data is in the
ViewDrop folder on the server.
The Cube is building successfully, it just does not include the additional
hours logged for the past 2 weeks for this project plan. All other projects
have correct AWP numbers in the Cube.
Any ideas would be appreciated.