I
Ian Wolstenholme
Hi
From the perspective of resource availability, what is the difference
between choosing the option to "generate an OLAP Cube AND update resource
availability" and the option "generate resource availability only" ?
If the second option is chosen for a limited time frame (say one year)
because it takes a long time to build the cube, what is the impact then of
choosing to generate resource availability for say the next 5 years. And if
these options are chosen later for different time periods how is the
existing data affected as a result. For example if I choose to generate
resource availability now for the next 12 months, does this affect the
previous resource availability data? And dos it overwrite the availability
data that was already there, making it appear as if a resource is no longer
available ?
Depending upon the responses to the above, one might be tempted to ask what
is the point of generating resource availability data for any period OTHER
than earliest project start date and latest project start date ?
Just need some clarification as the documentation isn't very clear on this !
Thanks
Ian
From the perspective of resource availability, what is the difference
between choosing the option to "generate an OLAP Cube AND update resource
availability" and the option "generate resource availability only" ?
If the second option is chosen for a limited time frame (say one year)
because it takes a long time to build the cube, what is the impact then of
choosing to generate resource availability for say the next 5 years. And if
these options are chosen later for different time periods how is the
existing data affected as a result. For example if I choose to generate
resource availability now for the next 12 months, does this affect the
previous resource availability data? And dos it overwrite the availability
data that was already there, making it appear as if a resource is no longer
available ?
Depending upon the responses to the above, one might be tempted to ask what
is the point of generating resource availability data for any period OTHER
than earliest project start date and latest project start date ?
Just need some clarification as the documentation isn't very clear on this !
Thanks
Ian