J
John Horton
If a task has one resource that is assigned to 1 eday of work MS Project
correctly shows 24 hours of work. When reported by an OLAP Cube report, 24
work hours are shown. When reported by a Resource Availability view only 8
hours are shown to be used by the task.
I have no problem not using edays or ehours but was find this to be odd.
correctly shows 24 hours of work. When reported by an OLAP Cube report, 24
work hours are shown. When reported by a Resource Availability view only 8
hours are shown to be used by the task.
I have no problem not using edays or ehours but was find this to be odd.