OLAP Cube - different values

T

Thomas

Hi all,

currently we are discovering different values between MSP and OLAP
Cube in PWA for generic resources.
The problem even persists after re-publish all assignments.

Any ideas?

To be more precise....
MSP:
No work for one specific generic resource (even incl. "load summary
resource assignments" at MSP startup)
PWA (OLAP / Portfolio Analyzer):
60h work for January 2008.....!?

Regards,
Thomas

PS: We're using Project Server 2003 / SP3.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top