Do you need to generate an OLAP Cube for Resoruce Availability? It
appears that you don't need to and that you just have to select the
range and the frequency. I did both and told it to generate it
immediately but I still get nothing in the Available From and To
dates!!??

Anyone have any idea what I might be doing wrong?
 
R

Rick Roszko

Okay, if this isn't the answer, please repost because when people see that
there has been 2 posts on a question, they figure it's answered...

On the "View Assignments" page, after you select resources and click on
apply, a new set of links appear on the left hand column. It's probably
(default) on "Current Assignments". You need to click on "All assignments".
 
J

JimReid

Rick,

You are in a different area that I'm looking. In the RESOURCE area
there is a view called RESOURCE SUMMARY that I modified and called
_RESOURCE SUMMARY and added the two fields a) AVAILABLE FROM and b)
AVAILABLE TO which was in the field list for the view.

To update these two fields I read that you have to update the RESOURCE
AVAILABILITY via the ADMIN area. Suppose to go to ADMIN then MANAGE
ENTERPRISE FEATURES in the BUILD TEH OLAP CUBE area there is an option
just to update Resoruce Availability. when I run that it does't update
these two fields.

Any other ideas? I have reposted the question but haven't got anything
better than what you sent so far.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top