A
Anbu
Hi,
We have a Project Server 2003 installed for the past 1 year. The MSP cubes
were getting built without any problem. However since last week, the MSP
cubes are not getting built. In PWA, the status of cubes is shown as,
"The cube is currently being built."
This status is shown in PWA for days together and in Viewdrop folder i can
see the xml file relate to cube building staged. I had a look at the CPU
utilization and SQL Server process is working hard but viewnotify.exe process
seems to sit idle after a couple of hours of initial processing of the xml
file.
In Analysis Server, the MSP_ASSN_FACT and MSP_RES_AVAIL_FACT cubes are shown
as processed but the MSP_PORTFOLIO_ANALYZER is shown as Not Processed.
Other things tried:
1. Restarted the viewnotify.exe and tried processing the xml file. Result is
the same.
2. Restart the server and tried processing. Result is the same.
3. Delete the OLAP cube database and restored the same from backup. tried
processing. Result is the same.
Please share your thoughts.
We have a Project Server 2003 installed for the past 1 year. The MSP cubes
were getting built without any problem. However since last week, the MSP
cubes are not getting built. In PWA, the status of cubes is shown as,
"The cube is currently being built."
This status is shown in PWA for days together and in Viewdrop folder i can
see the xml file relate to cube building staged. I had a look at the CPU
utilization and SQL Server process is working hard but viewnotify.exe process
seems to sit idle after a couple of hours of initial processing of the xml
file.
In Analysis Server, the MSP_ASSN_FACT and MSP_RES_AVAIL_FACT cubes are shown
as processed but the MSP_PORTFOLIO_ANALYZER is shown as Not Processed.
Other things tried:
1. Restarted the viewnotify.exe and tried processing the xml file. Result is
the same.
2. Restart the server and tried processing. Result is the same.
3. Delete the OLAP cube database and restored the same from backup. tried
processing. Result is the same.
Please share your thoughts.