Olap Cube not updated

A

asuchi

Hi,
I am using MSP 2007 +SP1 and i have build a view based on an olap cube.
Part of the info is Actual Work Vs Work for each resource.
In only one of our projects the Actual Work, although seen in Porject Pro,
not shown in the Olap Cube view.

I have built the cube again, published the project but no actaul work...

Any Ideas?

Thanks
Avital
 
P

Paul Conroy

Ensure all projects are published "Before" you build the cube.

If this still doesn't work, delete the cube from AS and rebuild it from new
 