John Horton
If a task has one resource that is assigned to 1 eday of work MS Project
correctly shows 24 hours of work. When reported by an OLAP Cube report, 24
work hours are shown. When reported by a Resource Availability view only 8
hours are shown to be used by the task.
correctly shows 24 hours of work. When reported by an OLAP Cube report, 24
work hours are shown. When reported by a Resource Availability view only 8
hours are shown to be used by the task.