OLAP Cube <>Resource Availability (edays or ehours)

J

John Horton

If a task has one resource that is assigned to 1 eday of work MS Project
correctly shows 24 hours of work. When reported by an OLAP Cube report, 24
work hours are shown. When reported by a Resource Availability view only 8
hours are shown to be used by the task.
 
T

Thukral h

JOhn ,actually Ms project has a default option of working hrs i.e. 8 hrs
daily from 9am to 5pm and 5days a week .becoz of this you are only able to
see the 8 hrs against a single days activity .Change the option in Ms project
as required.
 