D
davis_mer
We are trying to calculate remaining resource availabilty for all the
resources across all projects he/she is assigned in Portfolio Analyzer. We
have tried to insert a new column called "remaining availability" with the
follow calculation "Availability - Work = Remaining Availability". Here is
the issue : It shows remaining work (Task C) = 8hrs when work = 0hrs, which
is not true as the resource is already assigned to Task A and B with no
remaining availabilty. Also, with the inclusion of this calculation its
pulling in projects that resources are not assigned to (eg: Task D).
Availability Work
Remaining
Resource A
Project A 8 4
4
Project B 8 4
4
Project C 8 0
8 (??)
Project D (not assigned) 8 0
8 (??)
Thank you.
resources across all projects he/she is assigned in Portfolio Analyzer. We
have tried to insert a new column called "remaining availability" with the
follow calculation "Availability - Work = Remaining Availability". Here is
the issue : It shows remaining work (Task C) = 8hrs when work = 0hrs, which
is not true as the resource is already assigned to Task A and B with no
remaining availabilty. Also, with the inclusion of this calculation its
pulling in projects that resources are not assigned to (eg: Task D).
Availability Work
Remaining
Resource A
Project A 8 4
4
Project B 8 4
4
Project C 8 0
8 (??)
Project D (not assigned) 8 0
8 (??)
Thank you.