Olap cube generation using schedule is not working. This has been working
until 2 weeks ago. When I kick it off manually, it is generated without any
problem but whne i have it scheduled to run everyday at a particular time, it
doesn't even initiate the built. No error messages in app. or sys log. Any
help is appreciated.

thanks
 
G

Gary L. Chefetz [MVP]

Ashok:

Could the account you use in COM+ for OLAP Administration become frozen or
has its password expired? This would be a likely cause for the system to
stop working suddenly.
 