When I clean up completed tasks that are older than say 4 weeks from the
Clean up Project Server database page, does this data get removed from the
OLAP cube and any possible reports run after this as well?

Thanks
 
D

Dale Howard [MVP]

Vaughn --

No. The tasks are simply removed from each user's timesheet in PWA. It is
not removed from the OLAP cube. Hope this helps.
 
V

Vaughn Fox

Great, thanks Dale.
Dale Howard said:
Vaughn --

No. The tasks are simply removed from each user's timesheet in PWA. It
is not removed from the OLAP cube. Hope this helps.
 