OLAP reports showing inaccurate cost values

R

Rasha A

I've entered baseline costs and actual costs in MS Project 2007 for several
projects.

I'm currently trying to generate Data Analysis reports to summarize these
values,

The reports summarize baseline costs and actual costs for each account
number over a period of six months. some actual costs show as 6, 7 or 8.
but they should be 0.

I check back in Project and find the values are truely 0. so where did the
6s and 7s come from?

any ideas?

thanks
Rasha
 
M

Marc Soester [MVP]

Rahsa,

have you check that the cube was rebuild since you changed the baseline?
Thanks
Marc
 