W
Willian T. Atherton
The cost value of a project in PWA shows 84k and when a I see it on Cube
views it shows zero.
I research the problem, using project server database documentation, I did
this:
1. I selected values from MSP_CUBE_ASSN_FACT, column ASSN_COST and it had 0
for the project
2. After, I selected the value from MSP_VIEW_PROJ_ASSN_STD, column
AssignmentCost, and it was zero too. Documentation says
MSP_VIEW_PROJ_ASSN_STD is the origin for values of MSP_CUBE_ASSN_FACT.
3. I imagined that cube views will show only costs where the project has
assignments with costs rates.
4. My projects has costs not associated with resources assignments, we type
costs in project professional.
5. Looking for examples to find out what is happening, I found a project
that doesn’t have resources and the cube view is showing the correct value.
However when I selected values from MSP_VIEW_PROJ_ASSN_STD it was zero too,
but when I did the same in MSP_CUBE_ASSN_FACT the values was there.
So I ask: Where or how the values go from project tables to project server
tables, and from it to views tables, and again, from it to cube tables? How
can I solve my problem?
Regards,
ps.: I have rebuilt the cube many times
Willian Atherton
EPM Consulting Services
views it shows zero.
I research the problem, using project server database documentation, I did
this:
1. I selected values from MSP_CUBE_ASSN_FACT, column ASSN_COST and it had 0
for the project
2. After, I selected the value from MSP_VIEW_PROJ_ASSN_STD, column
AssignmentCost, and it was zero too. Documentation says
MSP_VIEW_PROJ_ASSN_STD is the origin for values of MSP_CUBE_ASSN_FACT.
3. I imagined that cube views will show only costs where the project has
assignments with costs rates.
4. My projects has costs not associated with resources assignments, we type
costs in project professional.
5. Looking for examples to find out what is happening, I found a project
that doesn’t have resources and the cube view is showing the correct value.
However when I selected values from MSP_VIEW_PROJ_ASSN_STD it was zero too,
but when I did the same in MSP_CUBE_ASSN_FACT the values was there.
So I ask: Where or how the values go from project tables to project server
tables, and from it to views tables, and again, from it to cube tables? How
can I solve my problem?
Regards,
ps.: I have rebuilt the cube many times
Willian Atherton
EPM Consulting Services