S
Steven
We have a problem with our OLAP value for total Baseline Work being different
than the value in a project. In round numbers, the total Work = 5500 hours,
total Baseline Work = 5000, and current total Actual Work = 2500. However,
when loaded to OLAP, the value for cummulative Baseline Work = 4500. We
cannot determine what is the cause for the missing 500 hours in the OLAP
value. Any iideas what could cause this?
Thank You!
than the value in a project. In round numbers, the total Work = 5500 hours,
total Baseline Work = 5000, and current total Actual Work = 2500. However,
when loaded to OLAP, the value for cummulative Baseline Work = 4500. We
cannot determine what is the cause for the missing 500 hours in the OLAP
value. Any iideas what could cause this?
Thank You!