I have been working with project for quite some time now. I use an SQL
Server to store the project data. I have a simple question.
When I indent a task the parent task dates and durations change to
reflect the new task child. When I outdent the child task again
Project manages to get the old task dates(pre indent dates) for the ex
parent task and shows them. I just want to know where does project
store the old dates or duration of the parent task before the indent.
I have gone crazy trying to find out the field in which this is
stored, and will be very grateful if someone can help me out here
Thanks
Questaly
I have been working with project for quite some time now. I use an SQL
Server to store the project data. I have a simple question.
When I indent a task the parent task dates and durations change to
reflect the new task child. When I outdent the child task again
Project manages to get the old task dates(pre indent dates) for the ex
parent task and shows them. I just want to know where does project
store the old dates or duration of the parent task before the indent.
I have gone crazy trying to find out the field in which this is
stored, and will be very grateful if someone can help me out here
Thanks