S
Scott Q
Hi,
I have a situation where a bug has caused the existing project schedule I
have in MSPS to be unusuable. I intend on deleting/removing the existing
Project Schedule and uploading a new version to take its place. The project
has however started some time back, and timesheets and updates have been
completed against this original schedule.
If I remove the schedule, are there any adverse consequences to past data
submitted to this project? Should I just leave both projects in MSPS and
call the second one version 2 and instruct people to use that?
Many thanks
Scott
I have a situation where a bug has caused the existing project schedule I
have in MSPS to be unusuable. I intend on deleting/removing the existing
Project Schedule and uploading a new version to take its place. The project
has however started some time back, and timesheets and updates have been
completed against this original schedule.
If I remove the schedule, are there any adverse consequences to past data
submitted to this project? Should I just leave both projects in MSPS and
call the second one version 2 and instruct people to use that?
Many thanks
Scott