Hello,
I'm using Project Server 2007 with SP2. We recently noted that the Standard
Rate for resources is different from what we see in PWA Resource Center Views
and Project Pro Resource Information. The Project Pro shows the current rate
and PWA shows previous year's rates. I'm not sure how to refresh PWA views. I
tried kicking off a Reporting DB Refresh, checking-out-in Resource Pool. None
of that has worked so far. Has anyone seen this before ? How can make PWA
recognize current rates...maybe it is pointing to previous fiscal year
somewhere...?
Thanks
Nach.
I'm using Project Server 2007 with SP2. We recently noted that the Standard
Rate for resources is different from what we see in PWA Resource Center Views
and Project Pro Resource Information. The Project Pro shows the current rate
and PWA shows previous year's rates. I'm not sure how to refresh PWA views. I
tried kicking off a Reporting DB Refresh, checking-out-in Resource Pool. None
of that has worked so far. Has anyone seen this before ? How can make PWA
recognize current rates...maybe it is pointing to previous fiscal year
somewhere...?
Thanks
Nach.