Sara - EPM
Hi All,
In our environment, we are using shared tasks. For example, we add
resources to Task XX as needed.
We also utilize contractors with certain start/finish dates. Once I assign
the contractor to a task that started before his/her inception, timesheet now
says he/she has unsubmitted timesheet for that period, which is prior to when
he/she started working with us.
To prevent this, I change the Availible From/To fields in the resource's
information. If I assign him/her to a task prior to that Available From/To
date, I get a spooler error while publishing -- which I completely expect.
Is there a way to publish this assignment without getting the spooler error?
Moving the task start date is not possible. Splitting the task up is also
not possible. Basically, I want to assign new resources to existing tasks
but not have unsubmitted timesheet appear in PWA.
Thanks!
Sara
In our environment, we are using shared tasks. For example, we add
resources to Task XX as needed.
We also utilize contractors with certain start/finish dates. Once I assign
the contractor to a task that started before his/her inception, timesheet now
says he/she has unsubmitted timesheet for that period, which is prior to when
he/she started working with us.
To prevent this, I change the Availible From/To fields in the resource's
information. If I assign him/her to a task prior to that Available From/To
date, I get a spooler error while publishing -- which I completely expect.
Is there a way to publish this assignment without getting the spooler error?
Moving the task start date is not possible. Splitting the task up is also
not possible. Basically, I want to assign new resources to existing tasks
but not have unsubmitted timesheet appear in PWA.
Thanks!
Sara