On Resource Substitution

V

vincent

Here's something i do not understand.

Upon using Resource Substitution Wizard (to replace my generic resource) it
SEEMS to stop at a particular task on my project. Say if i have 40 tasks
that needs to be substituted, it ends at 30. What is STRANGER is that if i
assigned a Resource to any of the summary task above task 31, the
substitution would carry on further <meaning there are indeed suitable
resources for task 30 to 40>. And if all the summary task had been assigned
toa resource, the substitution wizard would run through the project without
incidence. My question is why this happens, seeing how all help books stated
that it is best practice NOT to assign resources to summary task.

hope you guys know what's going on.

vincent
 