I have a task that its duration is 1 day.

I want it to begin on May 8th and finish on May 8th, but when I type in the
info it forces it to finish a day late (May 9th).

This messes up all the tasks after it, pushing all of them a day later than
they are due.

HELP!!!!
 
G

Gérard Ducouret

Hello,

In your calendar, 8th may is not a nonworking day like in France?

Gérard Ducouret
 
J

Jmalenfant

Gérard Ducouret said:
Hello,

In your calendar, 8th may is not a nonworking day like in France?

Gérard Ducouret




Unfortunately it's not that simple (I wish). It is scheduled as a working day.

Julie :)
 
R

Roger M

For the duration try 8h or 7h, instead of 1d to see when you get it done on 5/8
What about your associated resouce is it available 8h per day?
 
J

Jmalenfant

Roger M said:
For the duration try 8h or 7h, instead of 1d to see when you get it done on 5/8
What about your associated resouce is it available 8h per day?

THanks!! Changing duration to 8 hrs worked.
The weird thing is it only worked for one resource and not the others??
Anyways After that , to line up other resources I had to put a constraint on
the finish day to finish no later than may 8th.
(I was trying to avoid using constraints as I'm using the 'priority numbers'
as a way to level it all, and constraints can make everything go to cr%^*p
sometimes.
But for now, problem solved, so Thanks!
 
J

Jan De Messemaeker

Hi,

Project does not work in days, but in minutes.
Go to tools, options, view, and select the upmost date format (the one with
1:33 in it)
Now watch the start and finish.
Does the task start at begining of day according to your working time
calendar?
Does it take exactly a day, in other words, is the time of day in finish
equal to time of day n start?

If the answer on any of these is no, you should read faq 5 in
http://www.mvps.org/project/faqs.htm

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
M

Mike Glen

Hi Jmalenfant,

Welcome to this Microsoft Project newsgroup :)

You might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top