I work in Project 2000 and wanted to know if there is a
way to show variance from the baselined date and also the
current date in one gantt bar, possible showing 2 or three
different colors, I had seen this once before, however I
don't have an idea how to acheive it.

I will be grateful for any help that you can provide me.

Thanks, June
 
S

Steve House [MVP]

You use the term "baselined date" in the singular and I'm not aware of such
a data point. There's baselined start date, baseline finish date, etc but
there's no such as a "baselined date" unless you are referring to the date
on which the baseline itself was created or saved. Likewise the current
date already is shown on the Gantt chart as a vertical dotted line going
from top to bottom of the chart at todays date in the timescale. It's not
an attribute of any particular task. Can you be more specific about what
you're trying to do here?
 