Sagandy
I want to allocate a one off payment to a resource (Let's say and engineer)
for their total work on a project. They will work on multiple tasks, that may
well be spread over several summary tasks. Other resources may well work on
some or all of these tasks. From my understnding, I can't put the figure in
as a cost-per-use, as this will get calculated for each task they are
assigned to. I also can't put this in as a fixed cost for a task, as they are
working on several Tasks. I simply want to make a one off payment for all
ther work on the project. How can I do this.
Thanks
Andrew
for their total work on a project. They will work on multiple tasks, that may
well be spread over several summary tasks. Other resources may well work on
some or all of these tasks. From my understnding, I can't put the figure in
as a cost-per-use, as this will get calculated for each task they are
assigned to. I also can't put this in as a fixed cost for a task, as they are
working on several Tasks. I simply want to make a one off payment for all
ther work on the project. How can I do this.
Thanks
Andrew