Piyusha --
What your project manager wants to do cannot be done. Simply stated, the
first predecessor is the ONLY true predecessor tasks. The other task, which
the PM says is a predecessor, IS NOT a real true predecessor since it do not
drive the successor task's Start date. So, I think it's time for you to
tell the PM that he/she is asking for the impossible, and that he/she needs
to rethink the logic of the project. Hope this helps.
Piyusha --
Based solely on your short description, I would say that the first
predecessor is the only real predecessor. So I would only link the first
predecessor to the successor task. Hope this helps.
- Show quoted text -
Hi Dale,
Let me elaborate it
One project leader need to create a specific link between 3
predecessors tasks and 1 successor task.
He want that the successor task as soon as the first predecessor is
finished.
For example
Task name start date Finish date predecessors
task1 6/12/2009 6/15/2009
task2 6/12/2009 6/16/2009
task3 6/16/2009 6/20/2009 task1,task2
So by MSP feature task3 will start on 6/16/2009 but the project
manager wants to start on 6/15/2009.
Is there any feature or setting in MSP by which we can do it. Please
detail How can he do that ?
Thanks for your answer in advance.