one resource + 2 tasks at teh same time

F

Filip - beginner

I've got 2 questions.
1st. When I have in one project 2 tasks not related to each other -
they can be done in the same time - and I assign the same resource to
those both tasks, project is not moving them to other time, so this
resource must work with 200% productivity or f.e. he must do 16 hours
work in 8 hs. How can project correct this automatically?
2nd. The same situation, but in project server - 2 or more projects
running at the same time with the same resources.

I use Project Professional 2003 with Project Server 2003.

Thanks

Filip
 
M

Mike Glen

Hi Filip,

Welcome to this Microsoft Project newsgroup :)

That's what resource levelling is for!

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #19 on Levelling, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top