One resource in multiple resource "groups"?

E

el00guapo

I'm trying to use the resource "group" field to further detail resource
capabilities/competencies. As such, there are of course multi-talented
people that fit into two or more competencies.

Is there a way to assign a resource to multiple groups? Ideally, when
looking at the resource sheet and grouping by "resource group" I would then
see some resources twice.

Thanks in advance for your help & advice.
 
A

Andrew Lavinsky

The only way to achieve what you want is to have two different resources
representing different skill sets but the same person.

Most people just create a custom field, tie it to a lookup table, and use
that to capture multiple skill sets - or you can create a task custom field
with the same specs and assign it at the assignment level for data mining.

Why are you trying to do this exactly?


- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top