R
Renate
I have 15 designers working on multi projects (architects,engineers) at any
given time as new projects come in daily and vary in length from 3 weeks to 3
years depending on the scope of work. How can I best allocate resources
without a)pushing out the dates expected (no constraints but have predessors
in tasks)for each estimate or design work(and using 5% or something else
extends dates)and....b)I know they can't be 100% for each as in reality its
maybe an hour one day and 3 hours the next. I do not track resource costs
just want to indicate that "Bob" is working on all these projects when I
report to mgmt. What is the best way to do this, or is there some better way
to show resource allocations but not extend the project to the year 2015 when
it has to be done in 2010? Or am I trying to get projects to do what I want
and not what it's suppose to?
given time as new projects come in daily and vary in length from 3 weeks to 3
years depending on the scope of work. How can I best allocate resources
without a)pushing out the dates expected (no constraints but have predessors
in tasks)for each estimate or design work(and using 5% or something else
extends dates)and....b)I know they can't be 100% for each as in reality its
maybe an hour one day and 3 hours the next. I do not track resource costs
just want to indicate that "Bob" is working on all these projects when I
report to mgmt. What is the best way to do this, or is there some better way
to show resource allocations but not extend the project to the year 2015 when
it has to be done in 2010? Or am I trying to get projects to do what I want
and not what it's suppose to?