One resource on a project working half time

B

bdesilva

I'm having a problem using on Project 2007. I want to assign one
resource to be available no more than 1/2 time. This can be between 8
and 5 but never available for more than 4 hours per day. So I created
a 1/2 time calendar and assigned it to him. This has no affect on the
leveling. He still shows the 8hpd as before. Any ideas?
 
R

Rod Gill

Try leaving the calendar on 8h but set the Units to 50%. Select Window Split
and make sure the Work value is correct. Units always = Work/Duration so a
5d duration and Units of 50% means 20h of work.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




bdesilva said:
I'm having a problem using on Project 2007. I want to assign one
resource to be available no more than 1/2 time. This can be between 8
and 5 but never available for more than 4 hours per day. So I created
a 1/2 time calendar and assigned it to him. This has no affect on the
leveling. He still shows the 8hpd as before. Any ideas?

__________ Information from ESET Smart Security, version of virus
signature database 4478 (20091003) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4478 (20091003) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top