C
Carrie
I have one task in a large project that is not using the correct server
progress method default, actual work done and work remaining.
All other task are fine, it's just one task. I have tried changing the
progress method via Customize-Published Fields for that specific task,
Republishing Assignments, nothing.
Any suggestions on could be happening? I just don't understand how one task
in a large project could be different?
Thank you in advance!
progress method default, actual work done and work remaining.
All other task are fine, it's just one task. I have tried changing the
progress method via Customize-Published Fields for that specific task,
Republishing Assignments, nothing.
Any suggestions on could be happening? I just don't understand how one task
in a large project could be different?
Thank you in advance!